Loading...
#12-5878 Change Order #5 (Hannula Landscaping & Irrigation, Inc.) CHANGE ORDER CHANGE NO. 5 (five) CONTRACT NO. 12-5878 BCC Date: 522/244-- Agenda Item: //G TO: Hannula Landscape & Irrigation Inc. Attn: Dale Hannula, Owner 28131 Quails Nest Lane Bonita Springs, FL 34135 DATE: April 18, 2013 PROJECT NAME: Radio Road East MSTU Landscape & Irrigation Project PROJECT NO.: PO 4500136845 Under our AGREEMENT dated May 22, 2012 You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: INSTALLATION OF DRAIN HOLES TO ENSURE PERCOLATION Description of Change: The installation of percolation drain holes was determined to be necessary in order to ensure proper percolation in planted areas. The project specifications called for minimum percolation rate of 2 inches per hour. Onsite inspection of each hole dug for trees indicated that a percolation hole was required to be dug for 81 tree plantings. Reason for Change: It is necessary for the plant health that percolation rate of 2 inches per hour be achieved at the time of planting of all tree plant materials. Failure to ensure proper percolation rate will result in the root-ball drowning in the hole it's planted within. Cost Factor Evaluation: The cost of each percolation drain at $98.00 for a 4 ft. depth(48") and 8 inch diameter is considered to be acceptable and achieves the desired 2 inch per hour percolation rate. Field investigations resulted in some modification to the specifications to allow for a reduced depth of installation for each drain to be 4 ft. versus the original specification of 6 ft. depth. This adjustment resulted in a reduction in unit cost for percolation drain installation. ADD NEW TASK ITEM #85 Description: Tree Sumps 8" diameter by 48" depth; Qty. 81 x $98.00 Ea= $7,938.00 NET CHANGE PERCOLATION DRAIN INSTALLATION: $7,938.00 Days added for Percolation Drain Installation: 26 Days added IRRIGATION SYSTEM ADJUSTMENTS Description of Change: Adjustment in quantities for irrigation material installation is due to value added changes, added irrigation coverage for trees, and reduction in the number of quick coupler valves. Reason for Change: One Additional irrigation valve is added to the irrigation system to cover an additional zone for irrigation to provide better coverage, additional bubblers are added to trees for better control of the amount of water applied to tree plantings. Cost Factor Evaluation: The unit cost for each item adjusted is per the bid unit cost. INCREASE EXISTING TASK ITEM#59 Description: Hunter 1.5" Electric Solenoid Valve; Qty. 1 x $370.00 Ea= $370.00 INCREASE EXISTING TASK ITEM#60 Description: Hunter 1.0" Electric Solenoid Valve; Qty. 1 x $330.00 Ea= $330.00 INCREASE EXISTING TASK ITEM#64 Description: Green Reflective Pavement Markers; Qty. 4 x $46.50 Ea= $186.00 INCREASE EXISTING TASK ITEM#63 Description: Toro 0-2 GPM Adjustable Flow; Qty. 114 x $74.00 Ea= $8,436.00 INCREASE EXISTING TASK ITEM#88 Description: Add Bubblers for Gumbo Limbo Trees&Royal Palms; Qty. 82 x $10.65 Ea= $873.30 DECREASE EXISTING TASK ITEM#57 Description: Quick Coupling Valves; Qty. -2 x $138.00 Ea= -$(276.00) NET CHANGE IRRIGATION ADJUSTMENTS: $9,919.30 MEDIAN#39 IRRIGATION CONDUITS Description of Change: An extension to the PVC conduit at median#39 was required due to the fact that the existing irrigation conduit did not extend beyond installed pavers at the median tip. Reason for Change: Conduit in medians is required to extend beyond any installed pavers so that the maintenance contractor can make any necessary repairs to the irrigation line without removing the pavers. Cost Factor Evaluation: The cost factor identified as $22.71 per each linear foot for 8 inch material is found acceptable. The cost factor identified as $7.30 per each linear foot for 4 inch material is found to be acceptable. The negotiated unit cost identified is added to the bid per the change. ADD NEW TASK ITEM#86 Description: 8" 1120-1220 Sch 80 PVC Solvent; Qty. 15 x $22.71 LF = $340.65 ADD NEW TASK ITEM#87 Description: 4" 1120-1220 Sch 80 PVC Solvent; Qty. 15 x $7.30 LF = $109.50 NET CHANGE MEDIAN#39 CONDUIT: $450.15 ALTERNATE IRRIGATION SYSTEM INSTALLATION Description of Change: An alternate irrigation control system was found to be necessary in that the original specified Motorola Irrigation Control system had been found to not function due to reasons which are currently under review and are currently being resolved. Reason for Change: A properly functioning irrigation control system is necessary in order to ensure plant material health. The non-function of the installed Motorola Control system resulted in the requirement to install an alternative irrigation control system. Cost Factor Evaluation: The cost factors involved with this change are for installation cost only. The cost factors are negotiated unit cost and lump sum. Each item is evaluated in terms of necessary labor and misc. material required for the installation of the material provided by county. ADD NEW TASK ITEM#89 Description: Installation only: I-Core 6-Station Controller Plastic (material supply By County); Qty. 1 x $293.00 Lump Sum(LS)= $293.00 ADD NEW TASK ITEM#90 Description: Installation only: I-Core 6-Station Modules (material supply By County); Qty. 3 x $86.00 Ea= $258.00 ADD NEW TASK ITEM#91 Description: Installation only: XCH 800 Hybrid 8-Station Outdoor(material supply By County); Qty. 3 x $113.00 Ea= $339.00 ADD NEW TASK ITEM#92 Description: Installation only: XCH 1200 Hybrid 12-Station Outdoor(material supply By County); Qty. 2 x $127.00 Ea= $254.00 ADD NEW TASK ITEM#93 Description: Installation only: Solar Panel Kits For XC Hybrid Controllers (material supply By County); Qty. 5 x $69.00 Ea= $345.00 ADD NEW TASK ITEM#94 Description: Installation only: Concrete Banjo Posts(material supply By County); Qty. 6 x $45.00 Ea= $270.00 NET CHANGE ALTERNATE IRRIGATION CONTROL SYSTEM: $1,759.00 Days added for Alternate Irrigation Control System Installation: 20 days added PLANT MATERIAL ADJUSTMENTS Description of Change: Certain tree plantings are required to be adjusted due to utility conflicts found after commencement of construction. Reason for Change: In coordination with Public Utilities Department the location of existing water lines were determined in the field and certain trees (Royal Palms)were determined to have root balls which were too large to be located in the original specified areas. The Royal Palms were removed from the project in the identified areas and smaller Buccaneer Palms were specified. Cost Factor Evaluation: The cost factors are based on existing bid unit cost. DECREASE EXISTING TASK ITEM#6 Description: Royal Palms; Qty. -4 x $267.00 Ea= -$(1,068.00) INCREASE EXISTING TASK ITEM#5 Description: Buccaneer Palms; Qty. 8 x $445.00 Ea= $3,560.00 NET CHANGE PLANT MATERIAL ADJUSTMENTS: $2,492.00 CHANGES TO CRUSHED SHELL INSTALLATION Description of Change: During construction it was noted that certain median areas were wider than the original plans had indicated. These areas were determined to require additional crushed shell material. Also during installation the quantity of stakes for the border of the crushed shell was increased as a value added item in that the original quantity (in contract)had not been sufficient to provide for a smooth curve in the border material. Reason for Change: To provide for additional crushed shell to cover the actual square footage of on- site conditions. Added quantity of stakes to ensure a smooth curve boarder for all crushed shell areas. Cost Factor Evaluation: The cost factors are based on existing bid unit cost and negotiated unit cost to be added to contract. INCREASE EXISTING TASK ITEM#25 Description: Crushed Shell Washed; Qty. 36 x $56.55 Ton= $2,035.80 ADD NEW TASK ITEM#97 Description: Terrace Board Stakes In Brown(20-Pack); Qty. 30 x $20.11 Ea= $603.30 NET CHANGE CRUSHED SHELL INSTALLATION: $2,639.10 BOND INCREASE AND MOT INCREASE ADD NEW TASK ITEM #95 Description: Bond Increase; Qty. 1 x $594.00 Lump Sum (LS) = $594.00 ADD NEW TASK ITEM #96 Description: Extend MOT; Qty. 1 x $1,200.00 Lump Sum (LS) = $1,200.00 NET CHANGE BOND & MOT INCREASE: $1,794.00 NET DAYS ADDED TO CONTRACT: 46 DAYS NET CHANGE TO CONTRACT: $26,991.55 FOR THE (Additive) Sum of: $26,991.55 (twenty six thousand nine hundred ninety one dollars and fivety five cents) Original Agreement Amount $467,914.63 Sum of Previous Changes $36,452.70 This Change Order add $26,991.55 Present Agreement Amount $531,358.88 The time for completion shall be increased by 46 calendar days due to this Change Order. Accordingly, the Contract Time is now 347 calendar days. The substantial completion date is June 30, 2013 and the final completion date is June 30, 2013. Your acceptance of this Change Order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs. IN WITNESS WHEREOF,the Contractor and the County have each, respectively, by an authorized person or agent, hereunder set their hands and seals on the date(s) indicated below. ATTEST,:; " '- ',!;, BOARD OF CTY COMMISSIONERS .:t,, ZOfFLORDA LLIE D tight E.Brock,- lerk: - -- -•• -,- Afe t aja Cbai Ian's Approved by the BCC on May 14 , 2013 'rt':xe.oni :,‘ `Tor*, \-ke.r.rz.1/4,nq J vvc.c_dr■c,Vr40r-cvn DESI ]?ROSE IONAL: `J Urban Green Studio / • By: %1;,A/ .4�.: , a _ ; Co ier" County Purchasing Department Administrative Services Division Change Modification Form Purchasing ® Contract Change Request ❑ Work Order Modification Contract#: 12- Change#: 05 (five) PO/Work Order#: Project Name: Radio Road East 5878 4500136845 MSTU Landscaping & Irrigation Project Project#: Project Manager: Darryl Department: ATM Dept. Contractor/Firm Name: Hannula 4500136845 Richard Landscape & Irrigation Inc. Original Contract/Work Order Amount $ 467,914.63 5 o2 AO/P., Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 504,367.33' Last BCC Approval Date; Agenda Item# Current Contract/Work Order Amount $ 504,367.33 SAP Contract Expiration Date (Master) Dollar Amount of this Change $26,991.55 13.56% Total Change from Original Amount Revised Contract/Work Order Total $531,358.88 5.35% Change from Current BCC Approved Amount Cumulative Changes $63,444.25 5.35% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original completion date: Last approved completion date: Revised completion date (includes this 01/14/13 05/15/13 change): 06/30/13 Number of days added : 46 days Each step on the contract modification checklist form has been reviewed prior to me submitting for approval DR_ (this box must be initialed by Project Manager) ® Add new task(s) ® Change task(s) ❑ Delete task(s) ® Other(specify): Add time to contract 1. Provide a detailed and specific explanation of the requested change(s)to the task(s) and/or the additional days added: INSTALLATION OF DRAIN HOLES TO ENSURE PERCOLATION Description of Change: The installation of percolation drain holes is necessary to ensure proper percolation in planted areas. The project specifications called for minimum percolation rate of 2 inches per hour. Onsite inspection of each hole dug for trees indicated that a percolation hole was required to be dug for 81 tree plantings. The design consultant in pre-design investigation tested perculation rates and it was discovered that there may be a need to install perculation drain holes. As a result an alternate was added to the bid for installation of drain holes at 6' depth. Upon further field investigation after bid award, it was found that a 4' depth would be sufficient. Negotiations with contractor resulted in a savings of$14,742.00 Reason for Change: It is necessary for the plant health that percolation rate of 2 inches per hour be achieved at the time of planting of all tree plant materials. Failure to ensure proper percolation rate will result in the root-ball drowningin the hole it's planted within. Cost Factor Evaluation: The cost of each percolation drain at $98.00 for a 4 ft. depth (48") and 8 inch diameter is considered to be acceptable and achieves the desired 2 inch per hour percolation rate. Field investigations resulted in some modification to the specifications to allow for a reduced depth of installation for each drain to be 4 ft. versus the original specification of 6 ft. depth. This adjustment resulted in a reduction in unit cost for percolation drain installation. ADD NEW TASK ITEM#85 Description: Tree Sumps 8" diameter by 48" depth; Revised 5.16.12 Qty. 81 x $98.00 Ea= $7,938.00 NET CHANGE PERCOLATION DRAIN INSTALLATION: $7,938.00 Days added for Percolation Drain Installation: 26 Days added IRRIGATION SYSTEM ADJUSTMENTS Description of Change: Adjustment in quantities for irrigation material installation is due to value added changes, added irrigation coverage for trees, and reduction in the number of quick coupler valves. Reason for Change: One Additional irrigation valve is added to the irrigation system to cover an additional zone for irrigation to provide better coverage, additional bubblers are added to trees for better control of the amount of water applied to tree plantings. Cost Factor Evaluation: The unit cost for each item adjusted is per the bid unit cost. INCREASE EXISTING TASK ITEM#59 Description: Hunter 1.5" Electric Solenoid Valve; Qty. 1 x $370.00 Ea= $370.00 INCREASE EXISTING TASK ITEM#60 Description: Hunter 1.0" Electric Solenoid Valve; Qty. 1 x $330.00 Ea= $330.00 INCREASE EXISTING TASK ITEM #64 Description: Green Reflective Pavement Markers; Qty. 4 x $46.50 Ea= $186.00 INCREASE EXISTING TASK ITEM #63 Description: Toro 0-2 GPM Adjustable Flow; Qty. 114 x $74.00 Ea= $8,436.00 INCREASE EXISTING TASK ITEM#88 Description: Add Bubblers for Gumbo Limbo Trees & Royal Palms; Qty. 82 x $10.65 Ea= $873.30 DECREASE EXISTING TASK ITEM#57 Description: Quick Coupling Valves; Qty. - 2 x $138.00 Ea= -$(276.00) NET CHANGE IRRIGATION ADJUSTMENTS: $9,919.30 MEDIAN #39 IRRIGATION CONDUITS Description of Change: An extension to the PVC conduit at median#39 was required due to the fact that the existing irrigation conduit did not extend beyond installed pavers at the median tip. Reason for Change: Conduit in medians is required to extend beyond any installed pavers so that the maintenance contractor can make any necessary repairs to the irrigation line without removing the pavers. Cost Factor Evaluation: The cost factor identified as $22.71 per each linear foot for 8 inch material is found acceptable. The cost factor identified as $7.30 per each linear foot for 4 inch material is found to be Revised 5.16.12 acceptable. The negotiated unit cost identified is added to the bid per the change. ADD NEW TASK ITEM#86 Description: 8" 1120-1220 Sch 80 PVC Solvent; Qty. 15 x $22.71 LF = $340.65 ADD NEW TASK ITEM #87 Description: 4" 1120-1220 Sch 80 PVC Solvent; Qty. 15 x $7.30 LF = $109.50 NET CHANGE MEDIAN#39 CONDUIT: $450.15 ALTERNATE IRRIGATION SYSTEM INSTALLATION Description of Change: An alternate irrigation control system was found to be necessary in that the original specified Motorola Irrigation Control system had been found to not function due to reasons which are currently under review and are currently being resolved. The Alternate Irrigation Control system manufactured by Hunter Industries was provided to the contractor through a direct purchase order. Reason for Change: A properly functioning irrigation control system is necessary in order to ensure plant material health. The non-function of the installed Motorola Control system resulted in the requirement to install an alternative irrigation control system. Cost Factor Evaluation: The cost factors involved with this change are for installation cost only. The cost factors are negotiated unit cost and lump sum. Each item is evaluated in terms of necessary labor and misc. material required for the installation of the material provided by county. ADD NEW TASK ITEM #89 Description: Installation only: I-Core 6-Station Controller Plastic (material supply By County); Qty. 1 x $293.00 Lump Sum (LS)= $293.00 ADD NEW TASK ITEM #90 Description: Installation only: I-Core 6-Station Modules (material supply By County); Qty. 3 x $86.00 Ea= $258.00 ADD NEW TASK ITEM#91 Description: Installation only: XCH 800 Hybrid 8-Station Outdoor (material supply By County); Qty. 3 x $113.00 Ea= $339.00 ADD NEW TASK ITEM #92 Description: Installation only: XCH 1200 Hybrid 12-Station Outdoor(material supply By County); Qty. 2 x $127.00 Ea= $254.00 ADD NEW TASK ITEM #93 Description: Installation only: Solar Panel Kits For XC Hybrid Controllers (material supply By County); Qty. 5 x $69.00 Ea= $345.00 ADD NEW TASK ITEM#94 Description: Installation only: Concrete Banjo Posts (material supply By County); Qty. 6 x $45.00 Ea= $270.00 NET CHANGE Revised 5.16.12 ALTERNATE IRRIGATION CONTROL SYSTEM: $1,759.00 Days added for Alternate Irrigation Control System Installation: 20 days added PLANT MATERIAL ADJUSTMENTS Description of Change: Certain tree plantings are required to be adjusted due to utility conflicts found after commencement of construction. Reason for Change: In coordination with Public Utilities Department the location of existing water lines were determined in the field and certain trees (Royal Palms) were determined to have root balls which were too large to be located in the original specified areas. The Royal Palms were removed from the project in the identified areas and smaller Buccaneer Palms were specified. Cost Factor Evaluation: The cost factors are based on existing bid unit cost. DECREASE EXISTING TASK ITEM #6 Description: Royal Palms; Qty. - 4 x $267.00 Ea= -$(1,068.00) INCREASE EXISTING TASK ITEM#5 Description: Buccaneer Palms; Qty. 8 x $445.00 Ea= $3,560.00 NET CHANGE PLANT MATERIAL ADJUSTMENTS: $2,492.00 CHANGES TO CRUSHED SHELL INSTALLATION Description of Change: During construction it was noted that certain median areas were wider than the original plans had indicated. These areas were determined to require additional crushed shell material. Also during installation the quantity of stakes for the border of the crushed shell was increased as a value added item in that the original quantity (in contract) had not been sufficient to provide for a smooth curve in the border material. Reason for Change: To provide for additional crushed shell to cover the actual square footage of on-site conditions. Added quantity of stakes to ensure a smooth curve boarder for all crushed shell areas. Cost Factor Evaluation: The cost factors are based on existing bid unit cost and negotiated unit cost to be added to contract. INCREASE EXISTING TASK ITEM #25 Description: Crushed Shell Washed; Qty. 36 x $56.55 Ton= $2,035.80 ADD NEW TASK ITEM#97 Description: Terrace Board Stakes In Brown (20-Pack); Qty. 30 x $20.11 Ea= $603.30 NET CHANGE CRUSHED SHELL INSTALLATION: $2,639.10 BOND INCREASE AND MOT INCREASE Revised 5.16.12 ADD NEW TASK ITEM#95 Description: Bond Increase; Qty. 1 x $594.00 Lump Sum (LS) = $594.00 ADD NEW TASK ITEM #96 Description: Extend MOT; Qty. 1 x $1,200.00 Lump Sum (LS) = $1,200.00 NET CHANGE BOND & MOT INCREASE: $1,794.00 NET DAYS ADDED TO CONTRACT: 46 DAYS NET CHANGE TO CONTRACT: $26,991.55 2. Provide detailed rationale for the requested change: The installation of percolation drain holes is recommended to ensure that a percolation rate of 2 inches per hour is obtained so that plant material health is not negatively impacted by the existing soil condition. Percolation drain holes are priced based on actual field conditions. The irrigation system adjustments are both value added and quantity adjustment based on existing bid unit cost. Median #39 conduit extension is necessary to ensure that the irrigation system conduit is in place for future expansion into median #40. The unit cost is negotiated and deemed to be industry standard rates for this type of installation. The installation of the alternate irrigation control system was determined to be necessary in that once the trees were already planted it was found that the Motorola control system did not function. In order to provide essential water to the planted trees it was necessary to install an alternative irrigation control system. Plant material adjustments are related to changes due to utility lines found to be in conflict with proposed plantings. Staff in coordination with Public Utilities determined that the use of smaller size palm trees would resolve the noted conflicts. - The change in quantity related to the installation of crushed shell material is determined to be a result of variations in the actual median widths versus the original data provided for the project. The actual quantity of material provided is verified by contractor's delivery tickets. Added stakes are valued added for visual effect in that a smooth line is more desirable than a ridged sharp edge for the borders of crushed shell areas. The smooth edge could only be achieved with installation of additional stakes beyond original contract. 3. Provide explanation why change was not anticipated in original scope of work: The percolation rate of the soil varies and therefore it would be impossible to determine if installation of percolation drain holes would be required for a given quantity of trees. The project bid did include an alternate for the drain hole installation and staff negotiated a decrease in price for drain hole installation based on actual field conditions. Utility conflicts found would not be known prior to construction as the actual verification of utility location occurs by the contractor as investigative soft digs are performed. Public Utilities was very helpful in assisting with verification of utlity line locations and making recommendations for alternative plantings. Quantity adjustments for crushed shell is related to the actual field conditions which varied from the Revised 5.16.12 original data provided from the roadway engineering project drawings. A `re-survey' was determined to be beyond the scope of the original project and not a wise use of the limited funds available for the project. 4. Describe the impact if this change is not processed: A certain portion of the trees planted would die due to the percolation rate not meeting the horticultural standard of 2 inches per hour. Also, the irrigation system would not function as the alternative control system would not be installated resulting in cost prohibitive hand watering of all plant materials. There would be conflicts with trees and the existing water-line found in coordination with Public Utilities. And there would be insufficient quantity of crushed shell to cover the areas called out for crushed shell due to variations in median width. Type of Change/ Modification ® 1. Planned/ Elective ® 2. Unforeseen ® 3. Quantity or price adjustment conditions/circumstance ❑ 4. Correction of error(s) ® 5. Value added ® 6. Schedule adjustment Change Requested By ® Contractor/Consultant ® Owner ® Using Department ® Design Professional ❑ Regulatory Agency (specify): ® Other(specify): Radio Road East MSTU Advisory Committee Purchasing Professional Participated in Negotiation of Change/ Modification: ❑ Yes ® No Approved b-: ` Date: 17 '3 icap.oj Name and Title: sa ' 2_013 ichar• MSTU Project Manger Reviewed bf L Dateet,Aiu • 4 11� � argr / 1//L Procuremen rategist's Name: Rhonda Cummings Revised 5.16.12