#08-5011-076 (WO Kyle Construction)WORK ORDER
Agreement for Fixed Term Underground Utility Contract #08-5011
Contract Date: March 11, 2008
Fixed Term Contract Expires March 19, 2014
(RFQ #08- 5011 -76)
This Work Order is for Underground Utility Construction services for work known as:
Project Name: FYI First Quarter Backflows
Project No: 70019.4.1
The Work is specified in the Request for Quotation, dated November 15, 2012 which is attached hereto and made a part of
this Work Order. In accordance with Terms and Conditions of the Agreement referenced above This Work Order is assigned
to: Kyle Construction, Inc.
Scope of Work: Per Quote Tabulation form attached and the following:
• Task 1
Install 3/4" BFP's and relocation of services less than 20ft from the existing meter
• Task 2
Install 1" BFP's and relocation of services less than 20ft from the existing meter
• Task 3
Install 1.5" BFP's and relocation of services less than 20ft from the existing meter
• Task 4
Install 2" BFP's and relocation of services less than 20ft from the existing meter
• Task 5
Relocation of services more than 20ft from the existing meter
Schedule of Work: Complete work within 210 days from the date of the Notice to Proceed which is accompanying this Work
Order.
Compensation: In accordance with Section 2 — Statement of Work for Agreement #08 -5011, the County will compensate the
Firm in accordance with following method(s): ❑Negotiated Lump Sum; ❑Lump Sum Plus Reimbursable Costs; ®Time &
Material; ❑Cost Plus Fixed Fee, as provided in the attached proposal.
Task 1
$
11 1,668.48 (TM)
Task 2
$
18,062.08 (TM)
Task 3
$
6,876.42 (TM)
Task 4
$
3,327.30 (TM)
Task 5
$
15.00 (TM)
TOTAL FEE
$
139,949.28
PREPARED BY:
,,0ooPTereme Shaidle,1"E., Project Manager
Planning and Proj Management Dept.
APPROVED BY:
Mark Sunya , Principal Project Manager
Planning and Project Man eme t Dept.
APPROVED BY:
T# Chmelik, P.E., Director
Planning and Project Management Dept.
�/- /3
Date
Date
Date
y I /z, / r3
RFQ #08- 5011 -76
Page I
WORK ORDER
Agreement for Fixed Term Underground Utility Contract #08 -5011
Contract Date: March 11, 2008
Fixed Term Contract Expires March 19, 2014
(RFQ #08- 5011 -76)
A-.
APPROVED BY:
f6ul Mattausch, W ter De rtment Director Date
APPROVED BY:
Nicole Parker, Procurement Strategist Date
APPROVED BY:
George Yilmaz, Public Utilities Administrator Ni21 N t3 �
ATTES Igz ` rt
DvYi;il Broo;,lerk
:By:
Attest as,
:;r►ignahtre only,
By�G
(Print Name /Title
Approved as to Form and
1 Suf ien
ounty Attorney
Collier
By \/ UV
Georgia A. Hiller, Esq.
Chairwoman
3
MISSIONERS
KyyCon, By
Charles AbraY n Nhu , n-i-
(Print Name /Title)
RFQ #08- 5011 -76
Page 2
r3dmir>iEae Services Divisrn
Rod sins
REQUEST FOR QUOTATIONS UNDER CONTRACT #08 -5011
"Annual Contract for Underground Utilities ",
Date: November 15, 2012
From: Nicole Parker, Contract Specialist
239 - 252.4270, Telephone Number
239 - 252 -6549, Fax Number
nicoleoarker(cD-colliergov.net
To: Prospective Vendors
Subject: RFQ #08-5011 -76
FY13 First Quarter Backflow Installation
As provided in the referenced contract, the Collier County Purchasing Department is soliciting
quotes for the referenced project.
RFQ Due Date:
December 7, 2012 at 3:00 P.M.
Non Mandatory Pre -Quote Meeting Date/Time.-
November 27, 2012 at 3:00 P.M.
Pre -Quote Meeting Location:
Distribution office - 4425 Progress Ave
Q&A Deadline:
November 30, 2012 at 3:00 P.M.
Number of Days to Final Completion:
21D days to Final Completion
Liquidated Damages:
N/A
Plans and Specs:
scope of Work, Address List and Parts Form
Descri lion
Size
Quantity
UOM
Price
Total
Install of BFP's and relocation of services less
3/4"
847
Each
$t31.44
$Ill, bbS. y
than 20 ft from the existing meter
Install of BFP s and relocation of services less
1"
137
Each
$131.84
$ o62.o
than 20 ft from the existing meter
Install of BFP's and relocation of services less
1.5"
31
Each
$ ZZI. $Z
$6,916.
than 20 ft from the existing meter
Install of BFP's and relocation of services less
2"
15
Each
$ZZL gZ
$ 332'1.
than 20 ft from the existing meter
Relocation of services more than 20 ft from
Varies
15
Each
$100
$ '(S Go
the existing meter
TOTAL
$139
Your quotation response for this project is due no later than the date and time specked above.
We will not accept any quotation responses later than the noted time and date. If your firm is
unable to respond electronically, your quotation must be received in the office of the Purchasing
Department at the above referenced address no later than the time and date specified. We look
forward to your participation in this request for information/quotation process. Performance and
payment Donds shaft be required if the lowest responsive quote exceeds $200,000: - - -
RFQ ContractDriven RevisedSeptember2009
1